February 12, 2024 • 1 min read

Providing FEED services for ABEL Energy’s Bell Bay Powerfuels project

We’ve been awarded front end engineering design (FEED) work for ABEL Energy’s flagship green hydrogen and methanol project at Bell Bay in Northern Tasmania.

Under the agreement, we’ll design and engineer the facility, while also providing procurement and construction services through to final investment decision (FID). We’ll also work with local Tasmanian engineering company, pitt&sherry, to tailor our delivery approach to the unique considerations of the region.

Four people standing together from pitt&sherry, Worley, ABEL Energy and Worley Consulting.
L-R: Dean Comrie pitt&sherry CEO, Mark Accadia Worley Location Director for Australia East, PNG & Mongolia, Rhys Tucker ABEL Energy CTO and Andrea Hosey, Managing Consultant Chemicals and Fuels, Worley Consulting

Decarbonizing the shipping industry with green methanol

The Bell Bay project will use 240 MW of renewable energy for water electrolysis, to produce green (renewable) hydrogen. This hydrogen will then be combined with carbon from a biomass source to produce green methanol.

As a transport fuel, green methanol can help to reduce the carbon intensity of the shipping industry. Most of the green methanol produced by the Bell Bay facility will be consumed by shipping companies, which will help avoid over 540,000 tonnes of CO2 per year compared with crude oil-based marine fuels.

The expected run time for the FEED stage of the project is 12 months. The facility is scheduled to commence production by 2028.

“We are very pleased to have appointed Worley and pitt&sherry to deliver the front-end engineering design for our flagship project. We already have a strong and collaborative working relationship and we have every confidence that together we will deliver an exceptional project,” said Rhys Tucker, Energy Chief Technology Officer at ABEL Energy.

“With a history of delivering in Bell Bay for almost 30 years, leading this next critical phase of ABEL Energy’s Bell Bay Powerfuels Project is a great example of building on our past to help deliver a lower carbon future. We look forward to applying our global expertise across the entire green methanol value chain to support this flagship project,” said Mark Accadia, Location Director for Australia East, PNG and Mongolia.

RENEWABLE HYDROGEN

This site uses small files called cookies to help us customize your experience. If you continue without changing your settings, we'll assume you are comfortable receiving cookies on the Worley.com website. However, if you would like to change your cookie settings you can do so at any time. To learn more see our Privacy Policy.